CIP Project Number: 19-009
Project Manager: Ted Hill
Project Description:
The current UV disinfection system was installed in 1998 as part of a larger upgrade. While the system has worked well to disinfect the wastewater, it has required substantial attention to address ongoing maintenance upkeep of hydraulic and electrical failures. The City has selected the Trojan Signa System to replace the existing Trojan 4000 system.
Approved Budget/Est. Cost (All Phases): $3,914,067
Estimated Schedule: Construction February 2020 thru September 2020