2021 Clarks Creek Elodea Removal

2021 Elodea Management - DASH

The regular-season elodea management window for 2021 is June 1 - August 1, 2021. The contract was awarded to Stumpy Tree Service at April 27, 2021, Council meeting and in-water work began on June 1, 2021.

Permitting Windows

The 2021 elodea management work will include work under the existing permit from the Washington Department of Fish & Wildlife (WDFW). The current Hydraulic Project Approval (HPA) permit expires in June 2023.

The permitting process with WDFW for the in-water work to remove overgrown elodea and invasive weeds includes the submittal of a Joint Aquatic Resources Permit Application (JARPA). The proposed work was reviewed, and a 5-year HPA permit was issued by WDFW. The JARPA detailed the Diver-Assisted Suction Harvesting (DASH) process and proposed an in-water area of work. The total project area is approximately 3 miles long, beginning just south of the 12th Ave SW bridge in Puyallup and ending at the 56th Ave E bridge in Pierce County.

For more information on the WDFW HPA program and process please visit the WDFW website

Current Totals-

60.1% Project Complete

9,722 Linear Ft. 

20,978 Bags Filled

Updated: 07/16/2021

All numbers are reported by the contractor, and verified by Project Engineer.

Daily Progress

Elodea Removal Date Elodea Removal Area(s) Elodea Removal Distance (LF) Elodea Removal Bags Filled Elodea Removal % Complete
6-1-21 1,5 340 464 2.1
6-2-21 1,5 193 432 3.3
6-3-21 1,5 307 382 5.2
6-4-21 1,5 335 488 7.3
6-7-21 1,5 553 457 10.7
6-8-21 1,2,5 527 408 13.9
6-9-21 2,5 200 510 15.2
6-10-21 2,5 361 782 17.4
6-11-21 no work n/a n/a 17.4
6-14-21 2,5 248 431 18.9
6-15-21 2,5 603 657 22.7
6-16-21 2,5 478 741 25.6
6-17-21 2,3,5 427 669 28.3
6-18-21 3,5 37 278 28.5
6-21-21 3,5 383 719 30.9
6-22-21 3,5,6a 417 890 33.4
6-23-21 3,4,6a 436 857 36.1
6-24-21 4,6a 378 758 38.5
6-25-21 4,6a 308 747 40.4
6-28-21 4,6a 233 926 41.8
6-29-21 4,6a 184 851 43.0
6-30-21 4,6a 155 822 43.9
7-1-21 4,6a 318 922 45.9
7-2-21 4,6a 200 912 47.1
7-5-21 no work holiday    
7-6-21 4,6a 87 612 47.7
7-7-21 4,6a 175 277 48.7
7-8-21 4,6a,7 172 575 49.8
7-9-21 6a,7 394 987 54.2
7-12-21 6a,7 330 974 54.3
7-13-21 6a,7 235 904 55.7
7-14-21 6a,7 456 930 58.5
7-15-21 6a,7 252 616 60.1
7-16-21        
  1. Ryan Rutkosky, P.E.

    Senior Civil Engineer

Additional Information

Project Photos

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9

2018-2023 Permitting

  • Hydraulic Project Approval, HPA (WA Fish and Wildlife) - new JARPA application
  • Shoreline Substantial Development Permit (City of Puyallup) - existing permit provides coverage through June 2023
  • State Environmental Policy Act project review (City of Puyallup) - existing permit provides coverage through June 2023

Elodea History on Clarks Creek

Management of excessive elodea in Clark’s Creek has been ongoing for more than 20 years in Puyallup. In 2012 a task force comprised of staff, Council, citizens, regulatory agencies, and other organizations worked together to develop agreeable solutions to the problem. The goal was to find sustainable solutions that would reduce the overall presence of elodea and sediment in Clark’s Creek, improving the health of the creek.

Diver-assisted Suction Harvesting (DASH) was identified by the 2012 Elodea Task Force as the main method for elodea removal starting in 2013 onward. In this process, divers enter the water from pontoon-type boats, using surface-supplied air. The divers hand-pull the elodea from the stream, and feed it into a suction hose. The plant material is suctioned to the surface of the water, into mesh bags located on the boat. When several bags are full, they are each transported to the shore, and removed from the project site. This process reduces the fragmentation of the elodea, and completely removes the plant from the stream so it cannot re-plant itself, or grow back. The process is modeled after similar successful DASH projects in Thurston County, Washington and New York.