WPCP Secondary Clarifier No. 3

CIP Project Number: 20-018

Project Description:

This project includes the installation of a new Secondary Clarifier No. 3 to meet future capacity needs at the City's Water Pollution Control Plant (WPCP). The project also includes installation of yard piping, electrical work, HVAC and mechanical work to integrate the new secondary clarifier into the treatment plant processes.

The City selected Gray & Osborne to design the project. Construction is anticipated in Summer of 2024.

Budgetary Cost (Construction Phase): $7.5 Million

Photos from G-O
  1. Jessica Wilson, P.E.

    Senior Civil Engineer