Permits and Applications

Please submit all applications through the CityView portal.

Civil Construction Permit

This document shall accompany all civil plan submittals.

  • This permit must be preceded with an application for a preliminary site plan approval and the issuance of a SEPA determination (if applicable) from the Planning Division.
  • If the project disturbs one acre or more, the applicant must apply for an NPDES Construction Stormwater General Permit from the Department of Ecology.
  • As part of obtaining the permit, the applicant is required to publish two public notices in a newspaper that has general circulation in Pierce County. The applicant must publish a public notice one time each week, for two weeks in a row, with seven days between publishing dates. A 30-day public comment is required after the second publication. 
  • For additional information, please refer to the Department of Ecology